NEUE Construction Updates [Dec. 2019]
Seasons Greetings!
Early Christmas present from the Construction milestone of NEUE Macquarie Park:
* Concrete pours to the Ground Floor slab are approximately 75% complete;
* Formwork is progressing to Level 1 of Building A;
* Lift cores to each building are progressively being ‘jumped’ with the structure and are currently between Level 2 and Level 3;
* Basement levels have been stripped and back propped with services installation progressing.